Scroll to top

      Granitor

      We are a family-owned Swedish corporation that through our companies develops sustainable solutions for tomorrow's community and industry.
      Read about our operations

      Contact us

      Granitor Group
      +46 10 470 70 00
      info@granitor.se

      Head office
      Stjärntorget 1
      169 79 Solna

      Contact us today

      Shortcuts

      About Granitor

      Responsible businesses

      Career at Granitor

      Cookie Settings

      Together to get there logo
      • Integrity and cookie policy
      • Employee login
      • Whistleblowing system

      Refinery & Petrochemical plants

      Case #1

      NITROGEN PLANT CONTROL SYSTEM RETROFIT IN PERTAMINA REFINERY UNIT IV CILACAP

      • Total Retrofit of Nitrogen Plant Control System in KPC Pertamina RU IV Cilacap

        Scope :

        Engineering, Programming, Panel Fabrication, Site Installation, Commissioning

        PLC Panel (Allen Bradley ControlLogix, Redundant CPU, Redundant I/O, PanelView HMI)

        Control Room HMI (Wonderware InTouch)

      • 4 (four) days plant shutdown for installation & commisioning

      Case #2

      LOCK HOPPER CONTROL SYSTEM (LHCS) UPGRADE IN PERTAMINA REFINERY UNIT IV CILACAP

      • LHCS controls catalyst regeneration sequence in CCR Platforming Unit (UOP Process)

        Scope of Work:

        Reverse Engineering of Logic & Sequence from existing program

        New Control Panel & Operator Workstation (Allen Bradley PLC & Wonderware HMI)

        Testing with process/plant simulator

        Site Installation, testing & commissioning/start-up

      • Only 3 (three) days unit shutdown

      Case #3

      TANK OVERFILL PROTECTION SYSTEM IN PERTAMINA REFINERY UNIT IV CILACAP

      • Scope : SIL-2 PLC Package (Modicon Quantum) for tank overfill protection in Tank Farm/Oil Movement.

      • Features:

        Pump and Rotork MOV (Pakscan controller) trip based on Tank Level Switch

        Alarm and Event Logging System.

        Bypass Mode For Maintenance


      Case #4

      AIR DRYER CONTROL PANEL FOR INSTRUMENT AIR SUPPLY IN PERTAMINA REFINERY UNIT IV CILACAP

      • Control panel retrofit for 3 unit air dryer package

      • Replace relay & timer circuit control with PLC & panel HMI

      • Rugged components & enclosure suitable for outdoor installation